Welcome Login

You are here

Recent Blog Posts...

  • OASIS Blogger's picture
    OASIS Blogger
    Hello, Industry Community! As promised, we are posting the latest version of the questions and answers about the OASIS draft solicitations.  We have grouped the questions/feedback as General, Clarification, or Recommendation.  Please read all three files.  
     
    Last Activity: 4/12/2013 4:09 PM
    in OASIS Interact Community
     
    Comments (0) |Be the first!
  • OASIS Blogger's picture
    OASIS Blogger
      Hello, Industry Community! With the recent release of the draft RFPs and our goal of maintaining an atmosphere of transparency and fairness, we have consolidated all of the questions and feedback we’ve been receiving in our OASIS inbox and have provided responses below. Please note that some questions may have been edited for brevity or clarity. Since we have received multiple variations of some questions, we have organized them by broad topic areas in responding.
     
    Last Activity: 4/5/2013 11:32 AM
    in OASIS Interact Community
     
    Comments (0) |Be the first!
  • OASIS Blogger's picture
    OASIS Blogger
    Hello everyone,  Last Thursday, the OASIS team released the draft RFPs for Industry review and collaboration.
     
    Last Activity: 4/4/2013 7:20 PM
    in OASIS Interact Community
     
    JohnfoleyDSA
     Jim, thanks for getting the draft RFP released.  The package is quite clear and well thought out.  Regarding the Industry Day on May 13th; can you provide logistical information at this time (e.g., time and location)? ...Read More
    OASIS Blogger
    Hi John, thank you for your feedback on the draft RFP. In response to your question, please continue monitoring this blog for forthcoming information regarding logistical information. We will be posting that information shortly. Jim
    trefoil
    As a person who has defended GSA and their government-wide contract vehicles in hostile fora for years, I feel very disappointed and betrayed by the OASIS draft.  It seems as though GSA has thrown away all their best practices in government-wide...Read More
    OASIS Blogger
    Thank you for your feedback and your obvious passion for GSA and its mission.  I would request that you use the Attachment in the draft RFPs to provide your specific feedback so that we can make any needed adjustments.Jim
  • OASIS Blogger's picture
    OASIS Blogger
    Hello Industry Partners, I know you are anxiously awaiting the release of the Draft RFP.  GSA promised it would be released in the summer of 2012 and we are earnestly working to keep that promise.   Our current plan is targeting mid-September, no later than the 18th, to release the Draft RFP.  We know that this falls dramatically in your typical year-end business cycle and aware that your B&P teams will be extremely busy and that some of you may be unable to give the Draft RFP attention before October 1st. 
     
    Last Activity: 4/3/2013 9:55 AM
    in OASIS Interact Community
     
    sthuotsadilova
    Please clarify if all past performance entries must come from Prime on and demonstrate all competencies.
    Ron Kubacki
    I notice there hasn't been a blog post for over 14 weeks.  Did the OASIS Draft RFP ever get released?  I've checked GSA Interact and FBO and can't locate any new information.  Can anyone shed some light?Thanks, Ron
    OASIS Blogger
    Hi Ron, and thank you for your question. I’m not sure what or where you are checking, but you are missing a lot of activity.  Perhaps you need to check your settings.  Our last blog posting was made on March 7, 2013 and can be found here...Read More
    s.alvarez
    I dont see it posted, but the Drafts went up in FBO on March 28th: Solicitation Number: OASIS_RFI and Solicitation Number: OASIS_SB_RFI (for Total Small Business Set-Aside).
    OASIS Blogger
    We posted a blog here on Interact announcing the release of the drafts, but thank you for reminding the community that the drafts are available on FBO. Jim
  • OASIS Blogger's picture
    OASIS Blogger
    Hello OASIS Interact-ers!  February is upon us and I’m sure you’ve all noticed that we have yet to post our draft Request for Proposals (RFP).  As I promised last month, here is an update on where we are.  As many of you  know, we have a new Commissioner here in the Federal Acquisition Service (FAS), Tom Sharpe.
     
    Last Activity: 3/27/2013 10:46 AM
    in OASIS Interact Community
     
    dlehman12
    Hi Jim, Relative to your comment above on a contractor having a Purchasing System and EVMS - what do you mean by "an offeror will be given credit" - if they have these? Thanks.
    chip
    In the context of proposal development, is there a discrimination being cosidered between "past performance" and "capabilites". Recognizing that the past performance of a given offer will only be evaluated...Read More
    OASIS Blogger
    Thanks for the question.  We don’t plan to evaluate “capabilities”.  We plan to evaluate experience and past performance as well as systems, certifications, and resources of a prime vendor.  As we have expressed...Read More
    lbutler100
    I understand that businesses will have to respond to the OASIS IDIQ RFP with a prime bid to be prequalified to bid on future task orders as a prime. Do the same rules apply for subcontractors, or can subcontractors not participate in the IDIQ RFP...Read More
    OASIS Blogger
    Hello and thanks for the question.  OASIS has no limitation on subcontracting, so any subcontractor may be selected at the task order level to perform on an OASIS task order.  Subcontractors do not participate in the initial award process....Read More
  • OASIS Blogger's picture
    OASIS Blogger
    Since releasing the OASIS Business Case, the most frequent questions we receive at GSA are about strategic sourcing and how it will be applied to OASIS.  I would like to use this update to address this issue directly and clarify key issues.
     
    Last Activity: 3/11/2013 12:14 PM
    in OASIS Interact Community
     
    betsey.hutton
    Hi Jim,Just wanted to clarify what you mean by a 50% SB Subcontracting Goal on the unrestricted OASIS vehicle. Does this mean that of the work that the contractor subs out (as needed/at the company's discretion) 50% must be to SB's, OR...Read More
    OASIS Blogger
    Hi Betsey and thanks for the question.  This means that of the work that gets subcontracted, 50% of that work should be going to Small Business.  Jim
  • OASIS Blogger's picture
    OASIS Blogger
    As we get closer to the release of the draft Request for Proposals (RFP), I thought it would be a good time to discuss GSA’s “Rules of Engagement” for interaction with our Industry Partners.
     
    Last Activity: 2/25/2013 10:17 AM
    in OASIS Interact Community
     
    bobfritz
    Please continue to set the pace for a new way of dealing with Industry for major solicitations. Many other agencies are stuck in the 90s, electing to host events that require travel to and from, parking, hours, expenses, and other logistics...Read More
    OASIS Blogger
    Thank you for your feedback, Robert. We really appreciate it.
  • OASIS Blogger's picture
    OASIS Blogger
    Hello to the small business community,
     
    Last Activity: 2/15/2013 7:42 AM
    in OASIS Interact Community
     
    Michael Sheetenhelm
    Good Afternoon Jim,I've gone through the different questions and looked to see if this had been asked previously, but could not find anything and I'm hoping you can help: Understanding that GSA intends for the SB Socio Economic Status...Read More
    jjamibidm
    Wondering if the requirement to recertify as a small business every year could be reconsidered, perhaps in favor of recertification after 5 years (or at least after a period significantly longer than a year). Under the current recertification...Read More
    OASIS Blogger
    Thanks for the question.  I’m not sure where you got the information that Small Businesses would have to recertify every year, but regulations state that Small Businesses have to recertify size standard at the 5 year point and at the exercise...Read More
    consultant
    Will Small businesses be allowed to prime in the Set Aside OASIS and also subcontract to a large business under the Full and Open OASIS?Thank you.
    OASIS Blogger
    Hi and thanks for the question.  The answer is a resounding “ABSOLUTELY”.  In fact, use of OASIS SB prime contract holders as subcontractors on requirements issued under the OASIS contract will be encouraged by the OASIS Program...Read More
  • OASIS Blogger's picture
    OASIS Blogger
    Hello, Industry Partners! We are glad to take an opportunity to share more information with you about the OASIS acquisition.
     
    Last Activity: 2/14/2013 4:24 PM
    in OASIS Interact Community
     
    Michael A. Scruggs
    Jim,The Redacted Business Case document provides a useful insight in GSA's OASIS strategy.On page 10 of the document, four bulleted socioeconomic categories are identified (i.e., 8(a), HUBZone, SDBOSB, and women-owned small business concerns). ...Read More
    Regina Gibson
    Hi Jim,Page 11 of the OASIS Business Case document contains Chart 1: Comparison of Potentially Duplicative Vehicles. This chart lists the PSCs for the four main OASIS PWS areas. PSC 410 (listed as "Financial Management Services" in Chart 1...Read More
    OASIS Blogger
    Hello RG and thanks for the catch.  This appears to be a typo in the table.  410 should be 710.  Jim
    Eyam
    Hello Jim,I have a few questions:Before the draft RFP is officially released, is there a more comprehensive document that summarizes the scope and envisioned guidelines of QASIS (other than the Business Case document)? Particularly the detailed scope of...Read More
    OASIS Blogger
    Hi Eric, and thank you for your questions. In response:1.  No.  We have discussed the scope of OASIS and OASIS SB extensively in blog responses and there are many slides devoted to it that our available in briefings on this website.  2....Read More
  • OASIS Blogger's picture
    OASIS Blogger
    Hello Industry Partners,
     
    Last Activity: 2/7/2013 6:10 PM
    in OASIS Interact Community
     
    kcdensmore08
    Good Morning Jim,Is a summary or PowerPoint of “The Strategic Sourcing of Professional Services: Is It the Next Step? Is It the Right Step?” going to be available online and is there a way to attend virtually?V/R,Katie
    Ventura
    Hi Jim -At this time, approximately 95% of our total effort is provided On-Government-site with the remaining 5% provided On-Contractor-site.Hope this information is helpful!Best regards,Jamie, Ventura
    OASIS Blogger
    Thank you very much for responding to the survey, Jamie. We appreciate it.  Jim
    speikin
    Currently ~90% of our effort is provided on site with the government and ~10% is provided on contractor site.Regards,Scott
    OASIS Blogger
    Thank you for your feedback, Scott.  Jim